How to plan a power supply system replacement without risking continuity of operation?

08/09/2026

Author: Andrzej Łapa

zasilacze dla energetyki

Replacing a power supply system in an operational facility is not simply a matter of replacing an old device with a new one. The main challenge is to carry out the work in a way that keeps automation, safety systems, telecommunications and other critical loads available throughout the switching process.

This issue affects industrial plants, infrastructure facilities, buildings equipped with BMS, data centres and power infrastructure installations. Even a brief power interruption can stop a process, cause loss of equipment monitoring, disrupt communication or require parts of the installation to be restarted.

The risk increases in systems that have been in operation for more than a decade. The documentation may no longer reflect the actual configuration, loads may have been expanded several times, and rectifiers, capacitors and batteries may be approaching the end of their service life. Modernisation should therefore be treated as an intervention in an operating facility, not simply as equipment replacement.

Safe preparation should begin with an inventory of the existing installation and an assessment of the required level of power supply continuity. Only then should the new system be selected and the switching procedure planned.

The first step is to identify what cannot be switched off

The first step is to identify the installations and devices that must remain powered at all times. Depending on the facility, these may include automation controllers, BMS, telecommunications equipment, access control systems, CCTV, safety systems, servers, process equipment or switchgear control circuits.

Not all loads require the same level of protection. For some, a short interruption or shutdown during a scheduled maintenance window may be acceptable. Others must remain operational without interruption. Therefore, it is useful to divide the loads into four groups:

  • loads requiring uninterrupted power supply,
  • loads that can be switched over during an agreed maintenance window,
  • loads that can be powered by a temporary system during the work,
  • circuits that can be safely switched off for the duration of the modernisation.

This classification makes it possible to maintain power where an interruption would have a real impact on the operation of the facility, without unnecessarily providing backup power for the entire installation.

An audit of the existing installation is the basis for the design

Selecting a new system based solely on an archived schematic or the sum of the loads’ rated power is risky. Before starting the design, the documentation should be compared with the actual installation, and measurements should be carried out on site.

The audit should cover at least:

  • nominal voltage and actual load currents,
  • transient loads and starting currents,
  • required backup time,
  • battery type, condition and configuration,
  • busbar, outgoing circuit and protection arrangements,
  • cable cross-sections and lengths, as well as voltage drops,
  • earthing arrangements and earth fault monitoring,
  • alarm and control signals and communication interfaces,
  • environmental conditions and available installation space.

Load measurement instead of assumptions

Measurements should cover both steady-state operation and load variations occurring during normal operation. In a battery-backed system, the simultaneous supply of the loads and charging of a discharged battery must be taken into account. This helps avoid both underestimating the required power and unnecessarily oversizing the system.

The switching procedure must be designed, not just the new system.

The greatest risk usually arises when the old power source is disconnected and the loads are transferred to the new system. The method used for this operation must be based on the installation schematic, load requirements and the user’s organisational constraints.

Depending on the facility, the following solutions can be used:

  • temporary DC or AC power supply system,
  • backup power path,
  • staged replacement of individual sections,
  • mobile rectifier-battery system,
  • maintenance bypass,
  • switching during a planned shutdown.

There is no single solution suitable for every facility. The temporary system must be selected based on the voltage, load, starting currents, required operating time and existing protection devices.

Parallel connection of DC power sources requires analysis

Similar nominal voltages of two sources do not necessarily mean that they can be safely connected in parallel. A voltage difference can cause a circulating current that depends on the source voltages, source impedances and connection resistance. The connection conditions, required measurements and sequence of operations should be specified in the design and switching procedure.

The procedure should specify the initial state of the installation, the sequence of operations, the persons responsible, the method of confirming each stage and the procedure for returning to the previous configuration.

The new system must supply the loads and work correctly with the battery.

A floating-operation power supply supplies the loads, keeps the battery charged and, after a battery discharge, should provide sufficient current to recharge it. Therefore, the device selection must take into account the maximum load, load characteristics, power reserve, required charging current and operating temperature.

In facilities requiring high availability, an N+1 configuration can be used. If one module fails, the remaining modules must continue to supply the required loads. If modules are to be replaced while the system is operating, the specific device must be verified for hot-swap capability, current-sharing method and conditions for safely disconnecting a module.

Battery and protection require separate verification

Modernisation is the right time to assess the condition of the battery and verify whether it still provides the required backup time. Rated capacity alone is not sufficient. The available capacity depends, among other factors, on temperature, discharge current, end-of-discharge voltage and battery ageing.

The charging method must be adapted to the battery technology. VRLA and OPzV batteries have different requirements, while lithium batteries require proper integration with the BMS. Charging and temperature compensation parameters should be taken from the manufacturer’s documentation for the specific battery type.

DC protection devices must be selected for DC circuits

A battery can deliver a short-circuit current many times higher than the system’s rated current. Protection devices must be selected based on the DC voltage, expected short-circuit current, required breaking capacity and pole arrangement. The principles used for AC circuits should not be applied automatically.

The selectivity of the main protection, outgoing circuits, battery and rectifiers must also be analysed. A fault in one circuit should be cleared as close as possible to the point of failure without interrupting the power supply to the remaining loads.

 

Modernisation includes automation, alarms and communication

The new system may operate correctly from an electrical perspective and still fail to provide adequate monitoring of the facility. Before the replacement, all signals transmitted to the BMS, SCADA or other supervisory system should be inventoried.

The following should be checked, among other things: power supply failure, battery operation, low voltage, earth fault, battery failure, loss of input voltage and protection trip indications. Voltage and current measurements, as well as digital communication, should also be reproduced.

What matters is not only connecting the wires but also ensuring the correct signal logic. Changing the interpretation of NO/NC contacts can cause false alarms in the BMS or SCADA system even when the power supply itself is operating correctly. The scope of integration via Modbus RTU/TCP, IEC 61850, PROFINET or potential-free contacts should be defined before installation.

Equipment must be adapted to the existing installation

In an active switchgear room or technical facility, it is not always possible to use a standard cabinet. Limitations may include dimensions, the location of cable glands and cable routes, cable entry arrangements, space for the battery, ventilation, floor load capacity and access for maintenance.

A structure designed to fit the existing infrastructure can reduce the extent of mechanical and cabling modifications. This shortens the time required on site and reduces the number of operations performed near live installations.

Testing must be planned before connecting the loads

Acceptance testing should not be limited to checking whether the device starts up. Before the loads are transferred to the new system, the connections, polarity, voltages, protection devices, charging parameters, local and remote signalling, communication, cooling and settings should be verified.

Functional tests should then be carried out under load, including a simulation of primary power failure and the transfer to battery operation. In critical systems, a load bank can be used to verify system operation without placing a load on the facility’s actual installation.

The scope of testing and acceptance criteria should be agreed upon before work begins. This ensures that all parties know which conditions must be met before the loads are transferred to the new system.

Checklist before starting the modernisation

  • Critical loads have been identified and the permissible power interruption time has been defined.
  • Actual load has been measured, including transient loads and starting currents.
  • The battery condition and required backup time have been verified.
  • Cable routes, conductor cross-sections and voltage drops have been checked.
  • Protection devices have been inventoried and their selectivity has been analysed.
  • The method of switching from the old system to the new one has been defined.
  • A temporary power supply has been planned where required.
  • Alarm, control and communication signals have been agreed upon.
  • The installation location and cable routing arrangements have been verified.
  • The switching procedure and return-to-previous-configuration scenario have been prepared.
  • The scope of FAT/SAT testing and acceptance criteria have been defined.
  • The work schedule has been agreed with the personnel responsible for the operation of the facility.

The greatest risk arises when the new system is designed in isolation from the existing installation. Therefore, modernisation should begin not with selecting the power supply system, but with understanding the facility, defining the required level of operational continuity and preparing a safe switching procedure.

Other technical articles

  • Uninterruptible Power Supply for Telecommunications and Remote Control Systems – How to Design a System for Power Outages

    25/08/2026

    Selecting floating-operation power supplies for telecommunications and telecontrol systems – key principles of system design, battery backup and monitoring

  • Guaranteed 24 V DC power supply in the power industry – how to ensure continuity of substation automation and telecontrol systems?

    03/09/2026

    Key principles for selecting DC power systems, battery backup, diagnostics and redundancy for substation automation and telecontrol systems

  • From SI48-10 to modern DC power systems – the development of telecommunications power supply technology

    11/08/2026

    Changes in telecommunications power systems: from the SI48-10 rectifier to modern SI48 DC power systems

  • Plan a safe power supply system replacement

    Are you planning to modernise or replace a power supply system in an operational facility without risking continuity of operation? Contact us — our engineers can help design a safe switching procedure and select the optimal power supply system.

    • 1

      After receiving your enquiry, we will contact you by phone or email.

    • 2

      During the call, we will discuss your requirements and propose suitable solutions.

    • 3

      If necessary, we will arrange additional technical consultations.

    • 4

      We approach each case individually, so you can be sure that our response will be tailored to your requirements.