A correct output voltage alone does not show how a power supply will respond to a sudden change in load, a mains power failure or a short circuit. In industrial and telecommunications systems, such events can interrupt the operation of connected equipment. That is why testing electrical parameters and verifying device responses under defined operating conditions are essential parts of MERAWEX quality control. We use, among other equipment, four Chroma 8000 ATS SMPS automated test systems for this purpose.
Why measuring voltage alone is not enough
A power supply may operate correctly under a constant load while responding too slowly to a sudden increase in current demand. Other issues may involve voltage ripple, inrush current or the operation of protection circuits. Some of these problems are difficult to detect during basic commissioning checks.
For the user, it is therefore important not only to know the parameters stated in the documentation, but also how they are verified. Controlled variations in input voltage and load make it possible to assess the power supply’s behaviour before installation. This helps identify deviations at a stage when troubleshooting is easier than in an operational facility.
Chroma systems in MERAWEX quality control
MERAWEX operates four Chroma 8000 ATS SMPS test systems. They support the inspection of power supply equipment, including floating-operation power supplies and solutions designed for industrial and telecommunications applications. They are complemented by independent test stations for electrical safety testing and other specialised inspections.
Chroma manufactures the 8000 ATS SMPS platform for automated testing of power supplies and other electrical power conversion devices. Its architecture allows different instruments to be integrated and the test station configuration to be adapted to the device under test. This means the scope of testing can be tailored to the requirements of each product.
In automated ATE (Automatic Test Equipment) stations, programmable power sources establish the input conditions, while electronic loads draw specified currents from the outputs. Measuring instruments record the power supply’s response. This setup enables multi-stage testing according to a predefined procedure, without manually setting each successive operating point.
PowerPro integrates instruments into a single testing process
The PowerPro software controls the test procedures run on the systems used by MERAWEX. It operates the instruments, sends commands, reads measurement results and enables reports to be generated. This makes individual measurements part of a planned inspection sequence.
The system first configures the instruments and establishes the required power supply and load conditions. It then performs measurements, compares the results against predefined limits and enables the results to be saved. Efficient communication between instruments is also important when running complex procedures. Optimising commands reduces unnecessary operations and streamlines successive tests.
For MERAWEX, a practical advantage of the Chroma platform is the ability to repeat a defined test sequence across successive devices. Automatic instrument configuration and measurement sequences shorten testing time, reduce the influence of manual operator settings and make results easier to compare. The software supports the testing process, while the scope of testing and evaluation criteria must reflect the power supply’s design, intended application and documentation requirements.
What we test depending on the power supply design
Not every product requires the same test procedure. For a floating-operation power supply, battery compatibility is important, while other devices may require greater emphasis on specific load conditions or protection functions. The Chroma platform allows us to combine the measurements needed to evaluate each device.
Voltage stability and operation under load
By varying the input voltage and output load, we can check whether the power supply maintains the required parameters across different operating points. The instruments record voltage, current and power. For multi-output devices, testing may cover individual power supply circuits, auxiliary outputs and circuits connected to the battery. This helps detect deviations that may not be apparent from a single measurement at nominal load.
Ripple and response to changes in current demand
The output voltage contains ripple and noise, while sudden load changes can cause transient deviations. Time-domain and noise analysers integrated with ATE systems enable waveform recording and evaluation of selected dynamic parameters. The results show whether the device response remains within the limits specified in the documentation. This is particularly important where even a brief voltage deviation could disrupt the operation of connected equipment.
Start-up and loss of input power
When switched on, a power supply may draw an increased current. Measuring the inrush current helps verify its behaviour against the design requirements. The test station can also simulate changes and interruptions in the input voltage. For floating-operation power supplies, depending on the test procedure, the transition to backup power and the ability to maintain the required output parameters are evaluated.
Protection functions
The presence of a protection circuit alone does not confirm that it operates correctly. By deliberately creating selected fault conditions under controlled test conditions, we can observe current limiting, output shutdown or the device’s behaviour after the cause of the protection event has been removed. Tests must be tailored to the design and carried out in accordance with an approved procedure to ensure meaningful results.
Reliable results require the right test procedure
Automation helps ensure repeatability, but it does not replace proper test preparation. The way the power supply is connected, connection quality, instrument configuration and stabilisation time all matter. At high currents, cable resistance can cause voltage drops that affect the results. When voltage or current changes rapidly, the measurement path must be capable of accurately capturing the waveform under test.
For this reason, quality control depends both on the capabilities of the Chroma system and on the selection of appropriate test conditions, limits and metrological supervision of the instruments. Electrical safety and electromagnetic compatibility (EMC) testing require suitable instruments and separate procedures. An ATE test station alone does not confirm a product’s compliance with a standard or replace any required testing and conformity assessment.
From measurement results to test documentation
PowerPro enables the generation of measurement reports. When the process is organised appropriately, each result can be linked to a specific unit, for example by its serial number. This allows the data to support non-conformity and complaint analysis, comparisons between devices and assessment of repeatability across successive production batches.
For the customer, this means that testing can be based on established criteria and that results are easier to analyse if a problem is detected. The scope of recorded data and the method of archiving should be tailored to the requirements of the specific process.
Testing as part of production preparation
At MERAWEX, the selection of test procedures combines the device’s technical requirements with the inspection process. This also applies to contract electronics manufacturing services (EMS). Agreeing on the scope of testing during production preparation helps define which parameters must be measured, which operating conditions must be simulated and how the results should be documented.
When introducing a new device or modifying an existing design, it is worth establishing:
- which parameters determine the correct operation of the connected equipment;
- which power supply and load conditions the tests should cover;
- which limits are specified in the technical documentation;
- which tests can be automated and how their results should be recorded.
Chroma systems help MERAWEX implement these requirements. They combine instrument control, measurement execution and result evaluation in a repeatable inspection process. The aim is to detect non-conformities before the device is released for use.
Other technical articles
EMS electronics manufacturing – from design to finished device
18/08/2026
From electronics design to the finished product – discover how we integrate design, manufacturing, assembly and quality control into a comprehensive EMS process
How to choose an EMS partner? 11 criteria worth checking before starting cooperation
05/08/2026
Find out how to evaluate an electronics manufacturing services (EMS) provider and choose a partner for long-term cooperation
How Do EMC and Pre-compliance Testing Reduce the Development Costs of Industrial Power Supply Systems?
23/06/2026
Learn how EMC testing and pre-compliance testing help identify issues at the prototype stage, reduce certification costs and accelerate the market launch of industrial power supply systems
Select the right power supply for your production needs
Planning to introduce a new power supply or electronic device into production? Send the MERAWEX technical team your requirements and project documentation. Together, we will define the parameters to be checked, the scope of testing and the method for verifying the device before serial production begins.
-
1
After receiving your enquiry, we will contact you by phone or email.
-
2
During the call, we will discuss your requirements and propose suitable solutions.
-
3
If necessary, we will arrange additional technical consultations.
-
4
We approach each case individually, so you can be sure that our response will be tailored to your requirements.